Home MenuGreenbelt Lake Dam Repairs
Project Plans available here.
Project Update Newsletters
What to Expect During Construction
- Temporary Lake Path Closures
- A segment of the trail around Greenbelt Lake in the vicinity of the dam project will be closed from 10/28/19 through 11/10/19 to accommodate construction activities
- Lower Lake Level (4 or 5 Feet)
- Construction Equipment
- Construction Noise
- Strong odor
Estimated Project Schedule: September 3, 2019 to March 12, 2020
Project Schedule by Phase:
Phase 2A – Chimney Filter and Toe Drain
Start Date: September 3, 2019
End Date: December 11, 2019
Phase 2B – Embankment Raising
Start Date: December 12, 2019
End Date: December 31, 2019
Phase 3 – Spillway Repair
Start Date: January 2, 2020
End Date: March 12, 2020
For project information please contact Terri Hruby, Director of Planning and Community Development at 301-345-5417 or via email at thruby@greenbeltmd.gov.